Royston Solar Farm is a 14 MW solar PV project in Eastern that secured a Contract for Difference in Allocation Round 1. REPD lists the operator as Canadian Solar. Its strike price is £50.00/MWh in 2012 prices; 122 of the 377 solar PV contracts have a lower strike, and it is £5.44 below the technology average of £55.44. The 5 solar PV contracts awarded in AR1 range from £50.00 to £79.23/MWh, averaging £67.54. The plant is recorded as operational from 29 January 2016, but no CfD settlement has been published yet, so it may currently be selling its output at market prices rather than under the contract.
Projects with the most similar strike prices to this contract across all rounds.
| Project | Round | Strike Price | Capacity | Region | Status |
|---|---|---|---|---|---|
| Royston Solar Farm This project | AR1 | £50.00/MWh | 14 MW | Eastern | Not yet |
| Wick Farm Solar Park | AR1 | £50.00/MWh | 19 MW | — | Not yet |
| Charleston | AR6 | £50.07/MWh | 20 MW | Scotland | Not yet |
| MONTREATHMONT ENERGY CENTRE LIMITED | AR6 | £50.07/MWh | 34 MW | Scotland | Not yet |
| South Park Solar Farm | AR6 | £50.07/MWh | 15 MW | England | Not yet |
| STRATHRUDDIE ENERGY CENTRE LIMITED | AR6 | £50.07/MWh | 20 MW | Scotland | Not yet |
| Bramford Green Limited | AR6 | £50.07/MWh | 30 MW | England | Not yet |
| Sheraton Hall Solar Farm | AR6 | £50.07/MWh | 40 MW | England | Not yet |
| Glenniston Solar Farm | AR6 | £50.07/MWh | 39 MW | Scotland | Not yet |
| Gunthorpe Road | AR6 | £50.07/MWh | 50 MW | England | Not yet |
| Bilbo Solar | AR6 | £50.07/MWh | 25 MW | Scotland | Not yet |
| CLUMP FARM SOLAR LIMITED | AR6 | £50.07/MWh | 50 MW | England | Not yet |
| Tamworth Solar LTD | AR6 | £50.07/MWh | 30 MW | England | Not yet |
| Crays Hall Solar Farm | AR6 | £50.07/MWh | 26 MW | England | Live |
| Steeraway Solar Farm | AR6 | £50.07/MWh | 30 MW | England | Not yet |
| Skeeby Solar Farm | AR6 | £50.07/MWh | 39 MW | England | Not yet |
| Grey Street Solar Ltd (Fiskerton 3) | AR6 | £50.07/MWh | 50 MW | England | Not yet |
| Carlton Solar Farm | AR6 | £50.07/MWh | 38 MW | England | Not yet |
| Moat Farm Solar Farm | AR6 | £50.07/MWh | 20 MW | England | Not yet |
| Laynes Wood | AR6 | £50.07/MWh | 50 MW | England | Not yet |